Blue Castle Project

Planned nuclear power plant located near Green River, Utah

  • 8 min read
  • 4 chapters

Related on Lably

Through Watt, Equity (finance) and Meteorology

After winning a three-year legal battle over water rights, Blue Castle began reviewing construction companies to work on building the plant. The project is projected to cost up to $20 billion, though BCH projected only $13.4 billion as of January 2017. The plant is expected to produce up to 4000 short term jobs during construction and about 1000 long term jobs in the Green River area.

Public reaction has varied since the project was originally proposed. There are several local and national environmental groups who oppose the project.

History

Initial project

A project to build a $3-billion nuclear plant in eastern Utah was initially proposed in 2007 by Transition Power Development (TPD). TPD planned to have a minimum of two 1500 megawatt reactors active when the plant went live, though the proposed site could support three reactors. The plant is projected to "increase Utah's electrical capacity by approximately 50 percent". The plant was proposed in part to support a projected 2016 need for power from Rocky Mountain Power, the main supplier of electrical power to the state of Utah. Jon Huntsman Jr., the governor of Utah at that time, stated that he was opposed to any plan for a plant that did not include onsite spent fuel reprocessing. At the time of the proposal, TPD had obtained rights to about half of the water needed to run the proposed two reactors.

As part of the process, TPD started the process to lease 30,000 acre-feet (37 million cubic meters) from the Kane County Water Conservancy District in 2009 to supply some of the water needed for operating the plant. The project is projected to require about 55,000 acre⋅ft (68 million m3) of water to operate the proposed two reactors. Officials from Utah and TPD met in 2009 with both Secretary of Energy Steven Chu and Secretary of the Interior Ken Salazar regarding the fast-tracking of new nuclear programs in the western United States.

TPD became Blue Castle Holdings on September 28, 2009. About a week later, Blue Castle signed an agreement with Page Electric Utility (PEU)—an electrical utility company in Page, Arizona—detailing how PEU could become an equity owner in the proposed plant. BCH stated they had unanimous support for the plant from the Emery County Commission and the leadership of Green River, Utah in 2010.

In October 2011, BCH met with members of the Nuclear Regulatory Commission and local Utah agencies in hearings regarding site surveys, emergency planning, and environmental concerns regarding the placement of the proposed plant near the Green River. The company was also waiting for approval on applications to lease the 53,500 acre⋅ft (66 million m3) of water needed to operate the plant.

After a review period of more than two years, the water rights transfer was approved by an engineer working for the state of Utah. That decision was immediately challenged by a series of lawsuits. After hearing testimony in September 2013, a 7th District Court judge upheld the decision of the state engineer. The decision was appealed, but the appeals court upheld the decision of the 7th District Court judge in July 2016, stating the arguments by the plaintiffs were "often inadequately supported and briefed".

In 2017 BCH stated the licensing phase will go from 2017 to 2020. Following the bankruptcy of Westinghouse Electric Company, the manufacturer of the planned AP1000 reactors, in March 2017, the Blue Castle CEO said their plans were unaffected and "We’re going to wait and see who buys Westinghouse ... They’re not going to go away as a company." There have been no new announcements or updates on their website since 2019.

Projected cost

The initial projected cost given by Blue Castle (operating then as Transition Power Development) was $3 billion. By 2010, the cost of building the plant was estimated at $13–16 billion, which climbed to $18–20 billion by the end of 2016. BCH gave an estimated cost figure of $13.4 billion during a webinar in January 2017.

Site preparation

The site is located about 5 miles (8.0 km) west-northwest of Green River, Emery County, Utah. A geological study was completed on the proposed site which included ten 600 feet (180 m) boreholes which were then studied using optical and acoustic methods. These results were reviewed by the Nuclear Regulatory Commission, who stated that "the geotechnical activities were adequately controlled with an appropriate level of quality assurance and no issues were identified". Hydrological studies were done using 18 boreholes from 30–150 feet (9.1–45.7 m) in depth, and the data was being analyzed as of February 2016. Meteorological studies included two years of data collection.

BCH plans to store spent fuel rods onsite for at least 100 years.

Contracting and construction

Westinghouse will be producing the nuclear reactors for the power plant. In November 2016, BCH began looking for contractors to build the facilities.

BCH stated they plan to begin construction in 2023, have the first reactor online in 2028, and the second reactor online in 2030.

However, with no updates on the Blue Castle Holdings website since 2019, the project seems to be on hold and no new construction start date has been released.