Construction began in May, 2012 and was fully completed in August, 2013. It uses thin-film PV panels bought from Solar Frontier (CIGS type) and First Solar (CdTe type).
Phase 1 had a nameplate capacity of 60 MW and was connected to the grid in December, 2012.
enXco has signed a 25-year Power Purchase Agreement (PPA) with San Diego Gas & Electric (SDG&E) for the production from the station.
That clean electricity could offset roughly 74,000 tons of carbon emissions each year.
Production
More in Environment
Jimmy CarterPresident of the United States from 1977 to 1981United Nations Environment ProgrammeUN environmental response agencyVulnerable speciesIUCN conservation categorySurface runoffFlow of excess rainwater not infiltrating in the ground over its surfaceCritically endangeredIUCN conservation categoryGerald FordPresident of the United States from 1974 to 1977