The CPR-1000 is built and operated by the China General Nuclear Power Group (CGNPG), formerly known as China Guangdong Nuclear Power. Progressively more Chinese manufactured components were used in the units; the second unit built had 70% of its equipment manufactured in China, with a 90% Chinese content target for later builds.

Construction

On 15 July 2010, China's first CPR-1000 nuclear power plant, Ling Ao-3, was connected to the grid, having started criticality testing on 11 June 2010. It started commercial operations on 27 September 2010, with Ling Ao-4 starting commercial operation on 7 August 2011.

18 CPR-1000 reactors have been built as of December 2019. Besides Ling Ao unit 3 & 4, the CPR-1000 reactor has been realised in Fangchenggang (unit 1 & 2), Fangjiashan (unit 1 & 2), Hongyanhe (unit 1–4), Ningde (unit 1–4), Yangjiang (unit 1–4).