Dhaka Metro Rail

Mass rapid transit system in Bangladesh

  • 10 min read
  • 6 chapters

Related on Lably

Through Traffic congestion and Japan

The first section of MRT Line 6 commenced commercial operations on 29 December 2022 and the second section on 5 November 2023. The third phase, which will have an interchange with Line 1, Line 2 and Line 4, is set to be completed by 2026. Further expansion of MRT Line 6 is expected towards Savar Upazila and Tongi. Passengers get a 10% discount on the fare when using the MRT Pass or Rapid Pass. MRT line 6 currently operates daily from 7:30 am to 9:00 pm and on Fridays from 3:30 pm to 9:00 pm (7:10 am to 9:40 pm for MRT Pass/Rapid Pass holders). MRT Police provides security for the Dhaka Metro Rail.

History

To implement Dhaka's 20-year-long Strategic Transport Plan, the government of Bangladesh invited the Japan International Cooperation Agency to conduct a primary survey and feasibility study on the transport system of Dhaka in 2009–2010. In 2012, the executive committee of the National Economic Council approved the project. A loan agreement between the Bangladeshi government and the Japanese International Cooperation Agency was signed in January 2013.

Dhaka Mass Transit Company Limited, the agency responsible for the implementation of the first metro line, was formed in January 2013. The General Consultant, namely the NKDM Association, commenced work beginning in February 2014. In June 2013, Dhaka Mass Transit Company Limited was established by the government to implement the Metro Rail Lines across the city. Dhaka metro rail was opened by Prime Minister Sheikh Hasina on 29 December 2022.

History of MRT Line-6

Construction

The deal for the construction of the MRT Line-6, costing US$2.8 billion, was signed by the government of Bangladesh with the Japan International Cooperation Agency on 20 February 2013. Construction began on 26 June 2016 with an inauguration ceremony presided over by Prime Minister Sheikh Hasina. Civil engineering work was done by the Italian-Thai Development Public Company Ltd. and China's Sinohydro Corporation Ltd. JV, and a Tokyo-based construction company developed the depot's land.

Construction work was divided into eight packages, covering aspects like depots, stations and rolling stock.

Planning

When construction commenced in 2016, the Metro Rail was expected to open by the end of 2019. By 2018, this expectation was still held to, but by 2019, completion of phase one was delayed to December 2021. In 2018, the second phase was expected to be complete by December 2020. Eventually, these dates were pushed back, with phase one opening in 2022 and phase two expected in 2023. The main reason for the delays from 2020 to 2022 was the COVID-19 pandemic.

Cost and length changes

Originally, the project cost was Tk 219,850 million but it was later increased by Tk 114,870 million to Tk 334,720 million, although the full Project is not yet completed. The first route, originally projected to start from Uttara, a northern area of Dhaka, to Sayedabad, in the south of the capital, was eventually extended north to Uttara and truncated south to Motijheel. The original length which was 20.10 km (12.49 mi) has been increased by 1.16 km (0.72 mi) to 21.26 km (13.21 mi). It was planned to have 16 stations originally but it has been increased to 17 stations.

Misconceptions

The project was originally reported to be a 27 km (17 mi) underground metro rail line. It was later confirmed to be an elevated and underground metro rail project. In 2014, it was reported that 56 trains would run on the metro system. It was confirmed that 24 vehicles would run on the MRT Line 6. It was planned to have six lines.

Trial runs

MRT Line-6's train made its first run on 29 August 2021. It traveled from Diabari Depot to Mirpur 12. It successfully made its second run on 29 November 2021. It traveled from Uttara to Mirpur 10. The line's train made its longest trial run on 12 December 2021. It traveled from Uttara to Agargaon. The train ran for after invigoration has been run 4 stations along with mirpur to Agargaon station after several months other stations are open11.3 km (7.0 mi). It ran at 100 km/h (62 mph) for 9 km (5.6 mi) and ran at 15–20 km (9.3–12.4 mi) for the rest.