Gateway Generating Station

  • 7 min read
  • 3 chapters

Related on Lably

Through Transformer, Evaporative cooler and Carbon dioxide

Construction, which cost $386 million, began in 2001; the station began delivering power to customers in 2009. Its nominal capacity is 530 MW, with a peak capacity of 580 MW. It generates electricity using two combustion turbines, paired with heat recovery steam generators (HRSGs) that power one steam turbine. The facility is owned and operated by Pacific Gas and Electric Company (PG&E).

In June 2015, a lawsuit was filed against the Environmental Protection Agency to prevent the approval of the station's air-emissions permit; the suit was dismissed in October of that year. As of 2015, the only recorded injury that had ever occurred at the facility was in April 2009, when an employee tripped and chipped a tooth.

Construction

A proposal to construct the facility, originally called "Contra Costa Unit 8 Power Project", was filed with the California Energy Commission by Mirant Delta (now GenOn Energy Holdings) in January 2000. The proposal was certified in May 2001, at which point construction began. However, by 2002, Mirant was experiencing financial difficulties, and construction was suspended.

In July 2005, Pacific Gas & Electric acquired the partially-constructed plant from Mirant in a settlement agreement; in 2006 it was approved as a co-owner of Unit 8, and the process of filing paperwork was resumed.

PG&E wanted to change the name of the project from "Contra Costa Unit 8 Power Project" to "Gateway Generating Station"; this name was chosen to show that the "plant represents the 'Gateway' to the future of electric power generation" and was required to file a request for this. The Energy Commission approved this request five months later. During that time, in December 2006, PG&E became the sole owner of the project.

Construction finally resumed in February 2007, making Gateway the first new plant built by PG&E in nearly twenty years. The project was expected to cost about $370 million (equivalent to $544 million in 2023), employ as many as 400 workers at its peak, involve approximately one million worker-hours, and to provide electricity to customers by 2009. The engineering, procurement, and construction of the plant were managed by Black & Veatch. It was expected that PG&E would pay approximately $1.5 million to Contra Costa County annually in property tax.

The work for underground piping and powertrain equipment included loading, setting and alignment of heavy haul items, in addition to installation of pipe supports, piping, in-line instrumentation, platforms and enclosures. This portion of the work, along with associated management cost, encompassed 152,000 direct man-hours of labor over 21 months. By July 2008, construction was "two-thirds" finished. The gas turbines were first fired in November 2008; commercial operation, supplying power to nearly 400,000 customers, began on January 4, 2009. Randy Livingston, PG&E's vice president of power generation, said to the Brentwood Press that the project came "ahead of schedule, on budget, and we had no lost-time injuries during the entire construction of the plant". The overall cost of the plant was $386 million.