Guernsey Electricity

  • 7 min read
  • 3 chapters

Related on Lably

Through Watt and Alternating current

Business model

The cable connection to France provides most of the electric energy sold in Guernsey, but the power station still needs to maintain sufficient capacity to generate power should the cable fail. There are eight oil-fired diesel engines and three oil-fired gas turbines. These include two new diesel engines, given the names "Trudy"and "Freddy", costing £15m each, which were installed in engine room "D" in March 2017.

Environmental and cost considerations require the maximum use of the cable link, which is limited to 60MW.

  • Minimum demand is around 23 MW, with peak demand in 2022 of 95 MW.
  • Revenue from electricity sales in 2022 was £54.7m.
  • 29,763 customers in 2022
  • 340,726 MWh imported 2022
  • 30,006 MWh generated in 2022
  • 357,311 MWh distributed 2022
  • Power outages were an average of 23 minutes in 2022
  • In 2022 92% of electricity was imported using the cable link.

A retail shop is attached to the power station at North Side, Vale.

GE is governed by the Electricity (Guernsey) Law, 2001 (as amended) and is regulated by the Channel Islands Competition and Regulatory Authorities.

Undersea cables

In the mid-1970s investigations were undertaken to determine the practicality of an undersea cable. Jersey connected to France in 1984 (EDF1). No further decision was taken until 1996 when it was agreed to connect Guernsey to Jersey (GJ1) and lay a second 90 MW cable (Normandie 2) from France to Jersey, the work being completed in 2000 at a cost of £50m. The cables contain a 24 fibre optic communications cable.

A second 100 MW DC cable (GJ2) was planned to be installed, but was suspended after the existing GJ1 failed. GJ1 was replaced in 2019.

GE has invested heavily in the Channel Islands Electricity Grid, using debt to finance the investment, but losses in 2019 and 2020 as a result of the failure of the GJ1 cable requiring oil to be burnt for fuel, and the cost of the replacement GJ1, damaged finances.

The possibility of a 54 km (34 mi) direct cable to France designated GF1 was discussed in 2021.