Los Vaqueros Reservoir

Reservoir in Contra Costa County, California

  • 8 min read
  • 6 chapters

Related on Lably

Through Drainage basin, Reservoir and Habitat

Some 20,000 acres of land was acquired to provide for construction of the dam and its 1500-acre reservoir, as well as protection of 19,300 acres of associated watershed.

History

Los Vaqueros Reservoir is named for the 19th-century Mexican Rancho Cañada de los Vaqueros land grant that included its site. The Spanish word vaquero means "cowboy" in English.

Incursions of saline water into the Sacramento-San Joaquin River Delta from the San Francisco Bay has been a concern since the 1870s. This concern was one of the reasons CCWD was formed in 1936. A drought in 1977 caused salinity levels for the water supply to exceed public health standards. It forced CCWD to ration deliveries of fresh water to its customers.

An expansion project begun in 2010 raised the height of the dam to increase storage capacity from 100,000 acre-ft to 160,000 acre-ft of water. At the start of February 2017, the reservoir contained 133,700 acre-feet (164,900,000 m3) of water.

Project requirements

In 1988, voters approved funding of the Los Vaqueros Reservoir project to begin design and construction. It was a massive project. In addition to building the $61 million, 192-foot-tall dam, the district had to:

  • secure nearly 20,000 acres land for the dam and the watershed
  • build 12.8 miles of Vasco Road around the watershed at a cost of $27 million
  • relocate 20 electrical towers and 12 miles of gas line
  • build a new $20 million 10,000 horsepower pumping plant on Old River near Discovery Bay
  • construct a new $12 million transfer station with 8,000 horsepower pumps
  • build 20 miles of 6- to 8- foot diameter buried pipeline connecting all the new facilities with district's existing canal system in Antioch
  • commit to preserving the environment and respecting Native American and other historical sites in the watershed.

Construction timeline

  • Construction began Sept. 17, 1994.
  • By 1996, Vasco Road had been relocated around the eastern edge of the CCWD property. The original road was closed to travelers from just south of Marsh Creek Road to the present Los Vaqueros Road. Half of the pipeline from Old River to Discovery Bay had also been completed. Construction of the pump station was in progress.
  • The dam and most of the other major items were completed by December 1997. Filling of the reservoir with water began in February 1998, and was completed by January 1999, a year ahead of schedule.
  • The project dedication ceremony occurred in May 1998. The American Society of Civil Engineers named the project as the "Outstanding Civil Engineering Accomplishment" in the nation in that year.

2010–2012 expansion project

In March, 2010, CCWD approved a capacity increase of 60,000 acre-feet (74,000,000 m3). Costs will be passed on to those that receive water from the water District. Mitigation for the loss of sensitive wildlife habitat will be necessary. This increase is scheduled for completion in 2012. On July 14, 2012, the following portions of the expansion project were opened to the public:

  • Dam height increased by 34 feet (10 m) to the new height of 224 feet (68 m).
  • Addition of the John Muir Interpretive Center at the north end of the reservoir;
  • Provision of trails and shoreline fishing at the south end of the reservoir.

Barnard Construction Company, which was hired by CCWD to perform the reservoir expansion, employed Mechanically stabilized earth (MSE) technology to create the dam walls. Barnard subcontracted Reinforced Earth Company (RECo) to design and supply the MSE walls using its proprietary GeoMega™ MSE wall system, which utilizes precast concrete facing panels with GeoStrap® (high tenacity polymeric strips) as soil reinforcements. RECo also provided the precast concrete barrier and coping segments atop the newly expanded dam, reducing both cost and construction time for completion.

The south end of the reservoir reopened in October 2012, after revamping the marina. The storage level reached 132,900 acre-feet in 2013, before the CCWD began drawing down the level to serve user needs during the recent drought. Heavy rains in the watershed since October 2016, increased the level to more than 133,700 acre-feet (164,900,000 m3) at the end of January 2017, the all-time record for the reservoir.

2017 expansion proposal

A coalition of 12 Bay Area water agencies formally approved a study of expanding the reservoir by increasing the existing dam height by another 55 feet (17 m) to a total height of 273 feet (83 m). The proposed project would increase capacity of the reservoir from the present 160,000 acre-feet (200,000,000 m3) to 275,000 acre-feet (339,000,000 m3) at an estimated cost of $800 million.

In August 2017, the East Bay Times reported that the estimated cost of the expansion had increased from the previously announced $800 million to $914 million. It also reported that six environmental groups had written a letter of support for the proposed expansion to the California Water Commission. Groups signing the letter included Nature Conservancy, Audubon California, Planning and Conservation League, California Waterfowl Association, Defenders of Wildlife, and Point Blue Conservation Science. If the Commission grants the funds, construction could have started in 2022 and been completed in 2026, according to the Times. By 2024, the estimated cost of the expansion had increased to nearly $1.6 billion, and the California Department of Fish and Wildlife updated the relevant permit for drawing water from the reservoir, making the requirements stricter. There was also disagreement among the eight water agencies slated to participate in the project as to which agency should shoulder the most financial risk and pay for additional cost overruns if they came up. Multiple agencies have lowered their support for the project or withdrawn from it entirely, and the board of the Contra Costa Water District told its staff to draw up papers to pull their agency out of the deal, with a formal vote expected in November 2024. The East Bay Times described this move as "the death knell for the project," which cost the eight water agencies participating in the project over $4.4 million and thousands of hours of staff time.