Phase I

Phase I consists of 121 Vestas V82-1.65 MW wind turbines, for a total nameplate capacity of 199.65 MW. Groundbreaking ceremonies occurred on April 14, 2009. Phase I became operational in October 2009.

Horizon built a substation next to an existing AEP substation which was already within the wind farm site area. This allowed the wind farm to connect to the power grid without the need to build lengthy new transmission line at a cost of $1 million per mile.