North Anna Nuclear Generating Station

Nuclear power plant in Louisa County, Virginia

  • 7 min read
  • 7 chapters

Related on Lably

Through Watt and Fault (geology)

The plant has two Westinghouse pressurized water reactors which went on-line in 1978 and 1980, respectively. Together the reactors generate 1.79 gigawatts of power, which is distributed mainly to the greater Richmond area and to Northern Virginia. In March 2003, the Nuclear Regulatory Commission approved 20 year license extensions for both Units 1 & 2. Subsequent license applications for both units were submitted in 2020. The Nuclear Regulatory Commission approved the license for both Units 1 & 2 in August 2024. Unit 1's license will expire on April 1, 2058 and Unit 2's license will expire on August 21, 2060.

An artificial lake, Lake Anna, was constructed on the North Anna River to provide a reservoir of water coolant for use with the nuclear plant.

Dominion Energy currently owns nuclear power plants in Virginia (North Anna, Surry), Connecticut (Millstone), South Carolina (Virgil C. Summer Nuclear Generating Station), and Wisconsin (Kewaunee). North Anna is similar in design and appearance to Surry Power Station.

Unit 3

Dominion obtained regulatory permission from the NRC to build and operate an additional unit at the site in 2017. The additional unit 3 would be an ESBWR. but the project was placed on hold later in 2017 before construction started.

Timeline

Dominion Nuclear North Anna, LLC submitted its application for an Early Site Permit (ESP) for the North Anna site on September 25, 2003. The NRC issued the ESP on November 27, 2007. On the same day, Dominion submitted an application for a Combined Construction and Operating License (COL) for a 1,520 MWe GE–Hitachi Economic Simplified Boiling Water Reactor (ESBWR), designated as North Anna Unit 3.

In 2009, having failed to agree on terms for an engineering construction and procurement deal with GE-Hitachi to actually build the reactor, Dominion issued a new request for proposals from reactor vendors. In 2010, Dominion announced that it had selected a 1,700 MWe, US-specific version of Mitsubishi Heavy Industries' (MHI) Advanced Pressurized Water Reactor (APWR) for the potential Unit 3. The proposed reactor brought public protest. On August 7, 2008 six activists from the Peoples Alliance for Clean Energy were arrested at the North Anna Information Center for trespassing.

On October 29, 2010, Dominion president Tom Farrell told investors that Dominion had decided to slow its development of the proposed third reactor and wait until the combined construction permit-operating license (COL) was approved by the NRC before deciding to complete the project. This approval was expected in early 2013 but issued in May 2017.

In 2013, it was announced that the ESBWR design would be pursued after all. Dominion stated that it would amend its COL application to reflect the ESBWR technology by the end of 2013 and expected to receive the COL "no earlier than late 2015." Dominion noted that it had not yet committed to building a new unit at North Anna. In October 2015, the Virginia Attorney-General's Office called for the abandonment of the project because of the cost burden on consumers.

On January 19, 2017, the Nuclear Regulatory Commission announced that its staff had completed its Final Safety Evaluation Report for a Combined License for the proposed reactor. The report concluded there are no safety aspects that would preclude issuing the license for the construction and operation of the new reactor. On May 31, 2017, the Nuclear Regulatory Commission announced that it had authorized the issuance of a Combined License for North Anna. The license granted permission to build and operate an ESBWR design at the site. The license contained conditions, including specific actions associated with the NRC's post-Fukushima requirements for Mitigation Strategies and Spent Fuel Pool Instrumentation, and a pre-startup schedule for post-Fukushima aspects of the new reactor's emergency preparedness plans and procedures.

On September 6, 2017, Dominion Energy paused development activities related to North Anna Unit 3, a decision that nuclear consultant Jim Little suggests may have been due to market conditions and competition from natural gas. Since the federal construction and operating license is valid for 20 years, Dominion Energy may opt to resume the project if economic prospects for the plant improve within that period.