History

In 1985, there was a power generation and saline desalination plant in operation at the site, with commissioning support from Stuttgart-based Fichtner Consulting Engineers. Construction of the first plant 1 of the Shoaiba power station began in 1985 and second plant 2 in 1995.

The ABB-led consortium built a power station equipped with three turbines, heat recovery steam generators and ancillary power generation equipment. The first stage cost about US$850 million.

The first unit came into operation in July 2001. The other two units were completed in August 2003. The contract for construction of the second stage was awarded to a consortium led by Alstom Power.