Through Gujarat, Bhakra Dam and Surat

The dam is an earth-cum-masonry dam. Its embankment wall is 4,927 m long. Its earth dam is 105.156 meters high, whereas the masonry dam is 68.68 meters high. The dam's left bank canal feeds water to an area of 1,522 km2 and its right canal to 2,275 km2.

Vajpur fort, built by the Gaekwad dynasty of Baroda, was submerged in the reservoir. It can be spotted when water level in the reservoir is low.

Ukai Hydro Power Station

There are four hydro turbine units, each of 75 MW with a total installed capacity of 300 MW. All the above units were made by BHEL. Commissioning dates of units 1 to 4 are: 8 July 1974, 13 December 1974, 22 April 1975 and 4 March 1976.