The development is operated by BP Exploration (Caspian Sea) Limited on behalf of the Azerbaijan International Operating Company (AIOC) consortium. Peak oil production of approximately 823,100 barrels per day (130,860 m3/d) was reached in 2010. Production subsequently declined as the mature fields entered a period of declining output. Production averaged approximately 330,000 barrels per day in 2025. In the first quarter of 2026, production averaged approximately 325,000 barrels per day, with approximately 29 million barrels produced during the quarter.

BP reports that crude oil from ACG is exported through the Baku–Tbilisi–Ceyhan pipeline to the Mediterranean Sea, the Baku-Supsa Pipeline to Supsa in Georgia, and the Baku-Novorossiysk Pipeline to Novorossiysk in Russia. The ACG block also contains non-associated natural gas reserves. In 2024, BP and its co-venturers announced an agreement to advance the exploration, appraisal, development and production of these resources. The first non-associated gas production from ACG began in 2026.

In 2009, IHS CERA (Cambridge Energy Research Associates)ranked ACG third among 20 of the world's largest oil-fields, based on production. Total investment was estimated at US$20 billion at the time. In 2008, oil from the ACG fields accounted for approximately 80% of Azerbaijan's total oil production, including exports and domestic consumption. Contemporary estimates projected that the project could generate up to and was expected to generate up to US$80 billion in profits for Azerbaijan.

The Azeri Central East (ACE) platform, the seventh production platform in the ACG development, began oil production in April 2024.

History

Exploration of the Azeri–Chirag–Gunashli development started in the early 1990s. In January 1991, the Azerbaijani government announced separate international tenders for the exploration rights to the Azeri, Chirag and Gunashli fields. In June 1991, a consortium comprising Amoco, Unocal, BP, Statoil, McDermott and Ramco was formed to develop the Azeri field. Azerbaijan was represented in the consortium by SOCAR. Negotiations were later expanded to include all three fields. After Heydar Aliyev became President of Azerbaijan in 1993, talks with foreign companies were suspended, and Lukoil was invited to join the consortium. Negotiations resumed in 1994. The production sharing agreement (PSA) was signed by the parties on 20 September 1994 to develop the fields for an initial period of 30 years. The day the PSA agreement was signed is celebrated as Oil Workers' Day in Azerbaijan.

At the first stage, the consortium started development drilling at the Chirag field in August 1997. The first oil was produced in November 1997. This development stage was also known as the Early Oil Project (EOP). Initially, produced oil was exported through the Baku–Novorossiysk Pipeline. A contract for transporting oil through Russia to the Black Sea port of Novorossiysk was signed on 18 February 1996. Oil transportation through the pipeline began on 25 October 1997. To diversify export routes, construction of the Baku–Supsa Pipeline was agreed upon in 1996. The pipeline became operational in 1998 and was officially inaugurated in 1999. At the Chirag field, a water injection project was implemented in 1999, and drilling technology was upgraded in 2000.

The second stage of the development consisted of developing the Azeri field. Development of the Azeri field started in 2002. The Central Azeri living quarters arrived in Baku in July 2003, and the drilling modules arrived later that month. The Central Azeri jacket was completed in March 2004. To accommodate additional oil, the Sangachal Terminal was upgraded in March 2003. After the installation of the Central Azeri gas pipeline, the Central Azeri platform was launched in July 2004 and installed offshore by October 2004. Production started in February 2005. The Central Azeri compression and water injection platform topsides were launched in July 2005. The platform began injecting gas in May 2006

The West Azeri drilling modules arrived in Baku in August 2004, and the platform was launched in May 2005. The platform's topsides were installed in September 2005, and production started in January 2006. East Azeri drilling modules and living quarters arrived in Baku in June 2005, and the platform was launched in March 2006. The topside was installed in March 2006, and production began in October 2006.

The Deepwater Gunashli pre-drilling program started in December 2005. Drilling modules and living quarters arrived in Baku in June 2006. The platform became operational in April 2008.

On September 14, 2017, the Azerbaijan Government and the State Oil Company of the Republic of Azerbaijan (SOCAR), together with BP, Chevron, INPEX, Statoil, ExxonMobil, Turkish Petroleum (TP), ITOCHU and ONGC Videsh, signed an agreement to extend the PSA for ACG fields until 2049.

On April 19, 2019, SOCAR President Rovnag Abdullayev and BP’s regional president for Azerbaijan, Georgia, and Turkey, Garry Johns signed a contract worth US$6 billion. The final investment decision for the Azeri Central East (ACE) platform, to be built on the Azeri–Chirag–Gunashli (ACG) block, was made during a signing ceremony. Construction was scheduled to begin in 2019. Completion was planned for mid-2022.

The ACE platform was installed offshore in 2023 and began oil production on 16 April 2024. It was the seventh production platform installed as part of the ACG development.

In the first quarter of 2024, production was 339,000 barrels per day (53,900 m3/d), approximately one-third of its peak level. The ACE platform was brought on stream as production from the mature ACG fields continued to decline.

In 2024, BP and its ACG co-venturers also agreed to advance the exploration, appraisal, development and production of non-associated natural gas resources within the ACG contract area. Commercial production of non-associated gas began in June 2026.