Lably
Skip to content

Baku–Tbilisi–Ceyhan pipeline

Oil pipeline

  • 11 min read
  • 6 chapters

Related on Lably

Through Petroleum and Pipeline

History

Planning

The Caspian Sea lies above one of the world's largest collections of oil and gas fields. As the sea is landlocked, transporting oil to Western markets is complicated. During Soviet times, all transportation routes from the Caspian region were through Russia. The collapse of the Soviet Union inspired a search for new routes. Russia first insisted that the new pipeline should pass through its territory, then declined to participate.

In the spring of 1992, the Turkish Prime Minister Süleyman Demirel proposed to Central Asian countries including Azerbaijan that the pipeline run through Turkey. The first document on the construction of the Baku–Tbilisi–Ceyhan pipeline was signed between Azerbaijan and Turkey on 9 March 1993 in Ankara. The Turkish route meant a pipeline from Azerbaijan would run through Georgia or Armenia, but the route through Armenia was politically impossible due to the unresolved war between Armenia and Azerbaijan over the status of Nagorno-Karabakh. This left the circuitous Azerbaijan-Georgia-Turkey route, longer and more expensive to build than the other option.

The project gained momentum following the Ankara Declaration, adopted on 29 October 1998 by President of Azerbaijan Heydar Aliyev, President of Georgia Eduard Shevardnadze, President of Kazakhstan Nursultan Nazarbayev, President of Turkey Süleyman Demirel, and President of Uzbekistan Islam Karimov. The declaration was witnessed by the United States Secretary of Energy Bill Richardson, who expressed strong support for the pipeline. The intergovernmental agreement in support of the pipeline was signed by Azerbaijan, Georgia, and Turkey on 18 November 1999, during a meeting of the Organization for Security and Cooperation in Europe (OSCE) in Istanbul, Turkey.

On 1 July 2026, Azerbaijan's state-owned energy company SOCAR assumed operatorship of the Baku–Tbilisi–Ceyhan (BTC) oil pipeline from BP through its subsidiary, SOCAR Midstream Operations (SMO). The transfer covers all three sections of the 1,768-kilometre pipeline, which passes through Azerbaijan, Georgia, and Türkiye.

Construction

The Baku-Tbilisi-Ceyhan Pipeline Company (BTC Co.) was established in London on 1 August 2002. The ceremony launching construction of the pipeline was held on 18 September 2002. Construction began in April 2003 and was completed in 2005. The Azerbaijan section was built by Consolidated Contractors International of Greece, and Georgia's section was constructed by a joint venture of France's Spie Capag and UK Petrofac International. The Turkish section was built by BOTAŞ Petroleum Pipeline Corporation. Bechtel was the main contractor for engineering, procurement and construction. Detailed design and engineering contractor was ILF Consulting Engineers for the Turkish section of the pipeline, which is approximately over 1000 km.

Inauguration

On 25 May 2005, the pipeline was inaugurated at the Sangachal Terminal by President Ilham Aliyev of Azerbaijan, President Mikhail Saakashvili of Georgia and President Ahmet Sezer of Turkey, joined by President Nursultan Nazarbayev of Kazakhstan and United States Secretary of Energy Samuel Bodman. The inauguration of the Georgian section was hosted by President Mikheil Saakashvili at the pumping station near Gardabani on 12 October 2005. The inauguration ceremony at Ceyhan terminal was held on 13 July 2006.

The pipeline was gradually filled with 10 million barrels of oil flowing from Baku and reaching Ceyhan on 28 May 2006. The first oil was loaded at the Ceyhan Marine Terminal (Haydar Aliyev Terminal) onto a tanker named British Hawthorn. The tanker sailed on 4 June 2006 with about 600,000 barrels (95,000 m3) of crude oil.

Sign in to keep reading

5 more chapters are free with a Lably account.

More in Energy