Haiyang Nuclear Power Plant

  • 1 min read
  • 3 chapters

Related on Lably

Through Sustainable energy and Air pollution

History

Groundbreaking happened one month ahead of schedule on July 30, 2008. Construction of the first unit began in September 2009. Civil construction of Unit 1 was completed 29 March 2013. Fuel loading at Haiyang 1 began on June 22, 2018. First grid connection was on 17 August 2018. Unit 1 began commercial operation on 22 October 2018.

Construction of unit 2 started in June 2010, at that time the fourth Chinese AP1000 project together with the two units of the Sanmen NPP. Commercial operation began in January 2019, after having completed a full-power test run for a week (168 hours). Both units will provide together about 20 TWh of electricity to the grid of Shandong province.

On July 7, 2022, construction began on unit 3 after authorization had been granted.