Luton to Dunstable Busway

Public transport system in Bedfordshire, England

  • 4 min read
  • 5 chapters

Related on Lably

Through Soil contamination

History

Various studies had been carried out since 1989 which examined options for solving transit problems in the Luton/Dunstable Urban Area, including British Rail's Network SouthEast Plan published in May 1989. Bedfordshire County Council considered a number of possible schemes, which involved reopening or repurposing the former Dunstable Branch Lines, a disused railway line which had been closed to passenger traffic in 1967 under the Beeching cuts. One proposal was re-opening the railway to create a branch line of the Midland Main Line, to run Thameslink heavy rail services from Luton to Dunstable. This electrified, single-track route would have presented several challenges, in particular the lack of connection to the main line at Luton, which would have necessitated the construction of a grade-separated junction to the south of Luton Airport Parkway. An alternative heavy rail scheme was also evaluated, to reopen the line as a separate single-track route with passing loops, operated by a diesel-powered shuttle train service. Another proposal was to convert the line to segregated, twin-track light rail operation, with on-street operation on extensions to Houghton Regis and to Luton Airport.

A guided bus scheme was also considered, which would involve lifting the railway track and converting the trackbed to a segregated guided busway. This proposal was found to have particular advantages: it would be cost considerably less than the rail-based schemes, and the ability of buses to leave the busway and join the existing road network at designated points would allow better transport penetration of suburban areas. In 1996, the guided bus scheme was selected as the most cost-effective option.

Following local government reorganisation, the unitary authority of Luton Borough Council assumed control from Bedfordshire County Council in 1997, and took over the lead role in the busway project. A process of ongoing consultations, grant applications and a public enquiry delayed the project by several years.

Luton Borough Council's early announcements for the Busway indicated that it would be designed as a bus rapid transit system named Translink Expressway, operated with a fleet of articulated buses of the Phileas type, along part of the former Dunstable Branch Lines.

After 20 years of planning, the Busway took three years to construct, at a cost of £91 million. It was originally budgeted at £51 million, but costs increased due to underground utilities, soil contamination and the removal of Japanese knotweed. Design and construction was carried out by Arup and Parsons Brinckerhoff, including seven new bridges, and reconstruction of three bridges, bus stops and a new transport interchange at Luton Railway Station. The bulk of funding for the scheme came from the central government, with additional funds from Luton Borough Council and Central Bedfordshire Council, with additional section 106 contributions from developers. The Busway was opened 24 September 2013, five months later than scheduled, by Norman Baker MP, a Minister for Transport. The Busway took over approximately 7.7 miles (12.4 km) of the former railway line. Some remaining sections of disused railway were converted into pedestrian and cycling rail trail routes, with National Cycle Route 6 now following the line north-west between Dunstable and Stanbridgeford (via the Sewell Cutting nature reserve), and a southern section between from Welwyn Garden City to Wheathampstead now forming the Ayot Greenway.

Two new bus stops were added to the Busway system in early 2016 to serve the Chaul End area of Luton and Townsend Farm Road, near Houghton Regis.