Background

Construction of the earth-filled Saddle Dam D near Paksong, part of the $1.2bn (£915m) hydroelectric project by Xe-Pian Xe-Namnoy Power Company (PNPC), was begun in 2013. The hydroelectric project was a build-operate-transfer project. PNPC is a joint investment venture formed in March 2012 by SK Engineering and Construction (SK E&C), Korea Western Power (KOWEPO), Ratchaburi Electricity Generating Holding (RATCH), and Lao Holding State Enterprise (LHSE). SK E&C holds a 26% stake in PNPC, LHSE 24%, and RATCH and KOWEPO equally own the remaining shares. Part of an overall project to build two main dams and five auxiliaries, by the time of the collapse, it was near to completion and was intended to open for business in 2019.

Although landlocked, Laos is traversed by many intertwining rivers, which has encouraged their damming. The dam's construction was part of a scheme to expand Laos's electricity generating capacity to become the 'battery' of Asia", due to the country's location on the Mekong river and "abundant natural resources". The dam was intended to form a chain with other dams in the adjacent province of Champasak, across the Houay Makchanh, Xe Namnoy and Xe Pian rivers.

The dam, close to the Cambodian border, was intended to operate to a capacity of 410 megawatts, and earn revenue for the government by exporting 90% of the electricity produced to Thailand, which is more economically prosperous and developed compared to Laos.

Environmental pressure groups have long been critical of the Laotian government's ambitions regarding hydroelectric power, which have involved building multiple dams on the Mekong as well as on its tributaries. Concern has focused on potential damage to the flora and fauna and the animal societies dependent on the river to survive. Neighboring countries, like Cambodia and Vietnam that are downstream from the dams and rely heavily on the Mekong for fishing, food, agricultural irrigation, transport, tourism and cultural traditions, have expressed concern that Laos' hydroelectric ambitions could "disrupt vital ecosystems and their own river systems". The dam building program has regularly required the displacement and transplanting of inhabitants of villages that are found to obstruct dam construction, the benefits of which "are mainly enjoyed outside of the country", said environmental activists.

The company denied that the dam had collapsed, blaming recent heavy weather for the flooding, which had resulted in torrential rain filling the dam beyond capacity and overflowing, it said, which exacerbated the flooding which had already taken place downstream. A spokesperson for SK E&C said, "we believe that parts of the upper area of the dam were lost due to heavy rains and [then] the water overflowed". The International Rivers organization—whom the Washington Post described as "a nongovernmental group generally critical of such projects"—suggested that the collapse illustrates the "major risks" involved if construction is "unable to cope with extreme weather conditions", as, particularly in Laos, "unpredictable and extreme weather events are becoming more frequent". Indeed, an evacuation order had been in place for the area at the bottom of the dam due to cracks having been discovered in it. This damage had been reported to the company by South Korean contractors "at least a day before" the flooding, reported news outlets. Engineers from SK E&C apparently informed the PNPC that the top of the dam's structure had been washed away by 9 p.m. the previous night. Repair work was delayed because of the heavy rain. Furthermore, the Agence France-Presse (AFP) reported that it had obtained documents showing that "11 centimetres of subsidence was found at the centre of the dam" as early as the previous Friday. This subsidence was severe enough to prevent the use of emergency repair equipment.

On 11 September 2017, the reservoir for a dam under construction on the Nam Ao River in Phaxay district, Xiangkhouang Province collapsed after heavy rains in the area. In December 2016, the Xekaman 3 dam in Dak Cheung District, Sekong Province, had to be shut down after six years of usage due to damage in water tunnels.