Data validation and reconciliation

Technology to correct measurements in industrial processes

  • 13 min read
  • 6 chapters

Related on Lably

Through Data, Measurement and Observational error

Models, data and measurement errors

Industrial processes, for example chemical or thermodynamic processes in chemical plants, refineries, oil or gas production sites, or power plants, are often represented by two fundamental means:

  1. Models that express the general structure of the processes,
  2. Data that reflects the state of the processes at a given point in time.

Models can have different levels of detail, for example one can incorporate simple mass or compound conservation balances, or more advanced thermodynamic models including energy conservation laws. Mathematically the model can be expressed by a nonlinear system of equations F(y)=0 in the variables y=(y1,…,yn), which incorporates all the above-mentioned system constraints (for example the mass or heat balances around a unit). A variable could be the temperature or the pressure at a certain place in the plant.

Error types

Data originates typically from measurements taken at different places throughout the industrial site, for example temperature, pressure, volumetric flow rate measurements etc. To understand the basic principles of PDR, it is important to first recognize that plant measurements are never 100% correct, i.e. raw measurement y is not a solution of the nonlinear system F(y)=0. When using measurements without correction to generate plant balances, it is common to have incoherencies. Measurement errors can be categorized into two basic types:

  1. random errors due to intrinsic sensor accuracy and
  2. systematic errors (or gross errors) due to sensor calibration or faulty data transmission.

Random errors means that the measurement y is a random variable with mean y∗, where y∗ is the true value that is typically not known. A systematic error on the other hand is characterized by a measurement y which is a random variable with mean y¯, which is not equal to the true value y∗. For ease in deriving and implementing an optimal estimation solution, and based on arguments that errors are the sum of many factors (so that the Central limit theorem has some effect), data reconciliation assumes these errors are normally distributed.

Other sources of errors when calculating plant balances include process faults such as leaks, unmodeled heat losses, incorrect physical properties or other physical parameters used in equations, and incorrect structure such as unmodeled bypass lines. Other errors include unmodeled plant dynamics such as holdup changes, and other instabilities in plant operations that violate steady state (algebraic) models. Additional dynamic errors arise when measurements and samples are not taken at the same time, especially lab analyses.

The normal practice of using time averages for the data input partly reduces the dynamic problems. However, that does not completely resolve timing inconsistencies for infrequently-sampled data like lab analyses.

This use of average values, like a moving average, acts as a low-pass filter, so high frequency noise is mostly eliminated. The result is that, in practice, data reconciliation is mainly making adjustments to correct systematic errors like biases.

Necessity of removing measurement errors

ISA-95 is the international standard for the integration of enterprise and control systems It asserts that:

Data reconciliation is a serious issue for enterprise-control integration. The data have to be valid to be useful for the enterprise system. The data must often be determined from physical measurements that have associated error factors. This must usually be converted into exact values for the enterprise system. This conversion may require manual, or intelligent reconciliation of the converted values [...]. Systems must be set up to ensure that accurate data are sent to production and from production. Inadvertent operator or clerical errors may result in too much production, too little production, the wrong production, incorrect inventory, or missing inventory.