Power system operations and control

Power plant operation

  • 8 min read
  • 5 chapters

Related on Lably

Through Decision-making, Engineering and Marginal cost

Day-ahead operation

Day-ahead operation schedules the generation units that can be called upon to provide the electricity on the next day (unit commitment). The dispatchable generation units can produce electricity on demand and thus can be scheduled with accuracy. The production of the weather-dependent variable renewable energy for the next day is not certain, its sources are thus non-dispatchable. This variability, coupled with uncertain future power demand and the need to accommodate possible generation and transmission failures requires scheduling of operating reserves that are not expected to produce electricity, but can be dispatched on a very short notice.

Some units have unique features that require their commitment much earlier: for example, the nuclear power stations take a very long time to start, while hydroelectric plants require planning of water resources usage far in advance. Therefore, commitment decisions for these are made weeks or even months before prior to delivery.

For a "traditional" vertically integrated electric utility the main goal of the unit commitment is to minimize both the marginal cost of producing the unit of electricity and the (quite significant for fossil fuel generation) start-up costs. In a "restructured" electricity market a market clearing algorithm is utilized, frequently in a form of an auction; the merit order is sometimes defined not just by the monetary costs, but also by the environmental concerns.

Unit commitment is more complex than the shorter-time-frame operations, since unit availability is subject to multiple constraints:

  • demand-supply balance needs to be maintained, including sufficient spinning reserves for contingency. The balance needs to reflect the transmission constraints;
  • thermal units might have limits on minimum uptime (once switched on, cannot be turned off quickly) and downtime (once stopped, cannot be quickly restarted again);
  • "must-run" units have to run due to technical constraints (for example, combined heat and power plants must run if their heat is needed);
  • there is usually a single crew at the plant that needs to be present during a thermal unit start-up, so only one unit can be started at a time.