The plant was initially developed by British Gas (now National Grid) and Total Oil Marine. The three main plants have three main pipelines each coming ashore. The National Grid plant receives gas from the other main three plants. In total, St Fergus receives around 25% of the UK's gas. The land was purchased from the historical Mess family of St. Fergus

Total

The Total part of the refinery opened in September 1977 for the Frigg pipeline, with another section opening in 1978 for the Vesterled pipeline. The Queen opened this plant officially on May 9, 1978. Vesterled is owned by the Gassled partners.

Shell

The Shell plant opened in April 1982, being officially opened by Prince Charles in October 1982, taking gas from the Brent field, via the FLAGS pipeline. Gas came from the Fulmar field in July 1987, via the Fulmar Gas Pipeline, and from the Goldeneye field in October 2004.

Apache

This plant uses the SAGE pipeline from the Brae gas field. The plant also has two other main pipelines: Atlantic, Cromarty and the Britannia pipelines.