Lably
Skip to content

1999 Blayais Nuclear Power Plant flood

1999 flooding of the Blayais Nuclear Power Plant

  • 8 min read
  • 5 chapters

Related on Lably

Through Flood, Canal and Tide

The 1999 Blayais Nuclear Power Plant flood was a flood that took place on the evening of December 27, 1999. It was caused when a combination of the tide and high winds from the extratropical storm Martin led to overwhelming of the seawalls of the Blayais Nuclear Power Plant in France. The event resulted in the loss of the plant's off-site power supply and knocked out several safety-related systems, resulting in a Level 2 event on the International Nuclear Event Scale. The incident illustrated the potential for flooding to damage multiple items of equipment throughout a plant, weaknesses in safety measures, systems and procedures, and resulted in fundamental changes to the evaluation of flood risk at nuclear power plants and in the precautions taken. It was in some sense a forerunner of the 2011 Fukushima I nuclear accidents in Japan, but did not trigger the worldwide protection work on low-lying plants that the latter would.

Background

The Blayais plant, equipped with four pressurized water reactors, is located on the Gironde estuary near Blaye, South Western France, and is operated by Électricité de France. Due to records of over 200 floods along the estuary dating back to 585 AD, some 40 of which had been particularly extensive, the location of the plant was known to be susceptible to flooding, and reports of the 1875 floods mentioned that they were caused by a combination of a high tides and violent winds blowing along the axis of the estuary. The area had also experienced flooding during storms in the recent past, on December 13, 1981 and March 18, 1988. An official report on the 1981 floods, published in 1982, noted that it 'would be dangerous to underestimate' the combined effects of tide and storm, and also noted that the wind had led to 'the formation of real waves on the lower flooded floodplain'.

When the Blayais plant was designed in the 1970s, it was on the basis that a height of 4.0 m (13.1 ft) above NGF level would provide an 'enhanced safety level', and the base on which the plant was built was set at 4.5 m (15 ft) above NGF, although some components were located in basements at lower levels. The protective sea walls around the Blayais plant were originally built to be 5.2 m (17 ft) above NGF level at the front of the site, and 4.75 m (15.6 ft) along the sides. The 1998 annual review of plant safety for the plant identified the need for the sea walls to be raised to 5.7 m (19 ft) above NGF, and envisaged that this would be carried out in 2000, although EDF later postponed the work until 2002. On 29 November 1999, the Regional Directorate for Industry, Research and the Environment sent a letter to EDF asking them to explain this delay.

Sign in to keep reading

4 more chapters are free with a Lably account.

More in Energy