Through Japan, Korea under Japanese rule and Soviet Union

The Seikan Tunnel forms part of the standard-gauge Hokkaido Shinkansen as well as the narrow-gauge Kaikyō Line operated by the Hokkaido Railway Company (JR Hokkaido). Its name, "Seikan," is derived from the on'yomi readings of the first characters of Aomori (青森), the nearest major city in Honshu, and Hakodate (函館), the nearest major city in Hokkaido.

By total length, the Seikan Tunnel is the world’s longest undersea tunnel, surpassing even the Channel Tunnel (although the latter has a longer undersea section at 37.9 kilometres (23.5 mi) vs 23.3 kilometres (14.5 mi) for the Seikan Tunnel). It is also the deepest railway tunnel below sea level and was the deepest transport tunnel of any kind until Norway's Hitra Tunnel opened in 1994. It is the second longest main-line railway tunnel following Switzerland’s Gotthard Base Tunnel, which began operations in 2016.

History

The idea to connect the islands of Honshu and Hokkaido by a fixed link was proposed by the Imperial Japanese Army in the late 1920s for strategic reasons and was part of the army's idea of linking the Japanese main islands with Japanese-held Korea and the Sakhalin Islands, the latter then being divided with Japan and the Soviet Union.

The tunnel plan was handed over to the Ministry of Railways in 1946, with preliminary geological surveys and feasibility studies beginning on 24 April of that year induced by the loss of overseas territory at the end of World War II and the need to accommodate returnees. In 1954, five ferries, including the Tōya Maru, sank in the Tsugaru Strait during a typhoon, killing 1,430 passengers. The following year, Japanese National Railways (JNR) expedited the tunnel feasibility study. Also of concern was increasing traffic between the two islands; a booming economy saw traffic levels on the JNR-operated Seikan Ferry double to 4,040,000 passengers a year from 1955 to 1965, and cargo levels rose 1.7 times to 6,240,000 tonnes a year. Inter-island traffic forecast projections made in 1971 predicted increasing growth that would eventually outstrip the ability of the ferry pier facility, which was constrained by geographical conditions.

On 22 March 1964, the Japan Railway Construction Public Corporation was established, and excavation work began that year. In September 1971, the decision was made to commence work on the tunnel. Drilling began in 1972 from both sides—Hamana on the northern tip of Honshu, and Yunosato in Hokkaido. To avoid danger from earthquakes, the tunnel goes through dense volcanic rock. The tunnel was constructed using conventional construction methods, including blasting with the New Austrian tunneling method (NATM) and tunnel boring machines (TBMs). A Shinkansen-capable cross section was selected with plans to extend the Shinkansen network. Arduous construction in difficult geological conditions proceeded despite multiple challenges including drilling difficulties, tunnel floodings, and the 1973 oil crisis, which delayed completion of the tunnel. 34 workers were killed during construction.

The necessity for the project was questioned at times during construction, as ferry traffic predictions made in 1971 were overestimates. Instead of the traffic rate increasing as predicted to a peak in 1985, it peaked earlier in 1978 and then proceeded to decrease. The decrease was attributed to the slowdown in Japan's economy since the 1973 oil crisis and to advances made in air transport facilities and longer-range sea transport. Construction had begun during the heyday of the Seikan ferry route, but the ferry became mostly supplanted by air travel. On the freight side, due to the deterioration of labour-management relations at JNR at the time, including frequent strikes and legal compliance struggles, freight rail transportation stagnated and lost market share to ferries and coastal shipping.

By mid-1982, the tunnel had only 1,000 metres (3,300 ft) to complete. On 27 January 1983, Japanese Prime Minister Yasuhiro Nakasone pressed a switch that set off a blast that completed the pilot tunnel. Following this, on 10 March 1985, Minister of Transport Tokuo Yamashita symbolically bored through the main tunnel by detonating a dynamite charge on the last few meters of the earth.

The tunnel was opened on 13 March 1988, having cost a total of ¥1.1 trillion (US$7 billion) to construct (almost 12 times the original budget, much of which was due to inflation over the years). Construction of the tunnel itself was projected to cost ¥538.4 billion, but actually cost ¥745.5 billion, and construction of the line running through the tunnel was projected to cost ¥689 billion, but ended up costing ¥900 billion. To commemorate the opening, a commemorative 500 yen coin depicting the tunnel was issued by the Japan Mint in 1988.

Once the tunnel was completed, it became used by all railway transport between Honshu and Hokkaido, particularly conventional express trains, with all passenger services combined making up to 21 round trips daily (up to 50 round trips if freight trains are included). Similarly, the commuter ferry service between the two islands run by JNR was also discontinued. However, 90% of passenger transport is still by plane due to travel time and cost. For example, to travel between Tokyo Station and Shin-Sapporo Station by train takes eight hours, with transfer from Shinkansen to narrow-gauge express train at Shin-Hakodate-Hokuto Station. By air, the journey is 1 hour and 45 minutes, or 3 hours and 30 minutes including airport access times. Deregulation and competition in Japanese domestic air travel has brought down prices for the Tokyo-Sapporo route, making rail travel more expensive in comparison.

The Hokutosei overnight train service began after the completion of the Seikan Tunnel; a later and more luxurious Cassiopeia overnight train service was often fully booked. Both were discontinued following the commencement of Hokkaido Shinkansen services in March 2016, with freight trains being the only regular service utilizing the narrow-gauge line since then.

Because the tunnel is shared with freight trains, Shinkansen services cannot operate at their full design speed within it. While trains run at up to 320 km/h (200 mph) south of Morioka and 260 km/h (160 mph) outside the tunnel, speeds are limited to 160 km/h (99 mph) inside the tunnel. During major holiday periods, freight traffic is suspended, allowing Shinkansen trains to operate through the tunnel at up to 260 km/h (160 mph), reducing travel times.

Before the opening of the tunnel, research was conducted into a "Train on Train" where a narrow-gauge freight train would piggyback on top of a faster standard-gauge train. However, research ended in 2015 without being placed into use.

As of March 2019, Shinkansen services connected Tokyo Station and Shin-Hakodate-Hokuto Station in 3 hours and 58 minutes, with the final extension to Sapporo Station proposed to open in 2038 and expected to reduce the Tokyo–Sapporo rail journey to approximately five hours.